Worklot All free tools
Free tool · Subcontractors · UK retention and US retainage

Construction retention calculator

Enter the contract, the retention percentage and the completion date. Get the exact amount held, when each half is due back, and whether it is already overdue. Then put the release dates in your calendar so they stop slipping.

£
Cash locked in retention
£0
on a £0 contract at 5%
First half · at practical completion
£0
Due –
Second half · end of defects period
£0
Due –
Statutory interest if overdue
Nothing overdue yet.
Interest on late retention

All figures update instantly. Retention is normally deducted from each interim payment, so the amount locked builds up as work is certified and stays locked until the release dates above.

Get reminded before each release date, so you ask on the day it falls due.

Retention gets lost because nobody asks for it on time. Enter your email and we will send you these two dates now and a reminder 14 days before each one, with a release request you can forward to the contractor.

Done. Check your inbox for the release schedule.

How retention works, and why subcontractors lose it

Retention is a slice of every payment, usually 3% or 5%, that the party paying you holds back as security against defects. It is released in two halves. The first half (the first moiety) is due when the works reach practical completion. The second half is due when the rectification period ends and the defects certificate is issued, most often 6 or 12 months later.

The catch for subcontractors is that many subcontracts tie both releases to the main contract's dates, not your own. You can finish your package in March and wait for a main contract that completes in November, then a further 12 months for its defects period. Tick the box above to model that, because it is usually the real answer.

Standard form defaults

FormDefault retentionRelease
JCT Standard Building Contract 20163%Half at practical completion, half at the Certificate of Making Good
JCT Design and Build 20163%Same two-stage release
JCT Minor Works / Intermediate 20165%Same two-stage release
JCT subcontracts (SBCSub, DBSub)Mirrors the main contract, 3% or 5%Often keyed to main contract dates
NEC4 ECC / ECSNone unless Option X16 applies; percentage in Contract DataHalf at Completion, half at the Defects Certificate

Your contract can say something different. If it does, use the custom percentage and defects period above and treat the dates the calculator gives as the contract's dates.

How to get it released

  1. Ask in writing on the day it falls due. The release is a payment due under the contract. Apply for it in your next payment application, or as a standalone application, and state the amount.
  2. Watch the notice deadlines. Under the Construction Act the payer has to serve a payment notice and, if they intend to pay less, a pay less notice before the final date for payment. No valid pay less notice means the notified sum is due in full.
  3. Charge interest on late release. Once the final date for payment passes it is a late commercial debt. Use the late payment interest calculator to put a figure on it.
  4. Escalate. Statutory adjudication is available on any construction contract dispute, including retention, and typically produces a decision in 28 days.

VAT and CIS on retention

The VAT tax point for a retention payment is the earlier of the date you receive it and the date you issue a VAT invoice for it, not the date the underlying work was certified. That is a specific rule for retention in the construction industry, so do not account for VAT on the retention until it is actually released or invoiced. Where the domestic reverse charge applies to the supply, it applies to the retention too. CIS deductions are made when the retention is paid.

US retainage

Retainage is the same mechanism under a different name. 5% to 10% of each progress payment is withheld and released after substantial completion within a window set by the contract or by state statute. Many states cap retainage on public projects at 5%, some require it to be reduced or stopped once the project passes 50% completion, and most set a deadline in days for release once the conditions are met. Switch to US mode above to model a single release window; check your state's prompt payment statute for the cap and deadline that apply to you.

Common questions

When is retention released on a construction contract?

Under most UK standard forms, half at practical completion and half at the end of the rectification period once the defects certificate is issued. On subcontracts both dates are frequently tied to the main contract, which is why the second half can take two years or more to come back.

How much retention is normal in the UK?

3% under the JCT Standard Building Contract and Design and Build forms, 5% under Minor Works and Intermediate, and 5% on many subcontracts. NEC only holds retention where Option X16 is selected.

Can the contractor keep my retention if the client hasn't paid them?

Pay-when-paid clauses are unenforceable in UK construction contracts except where the paying party upstream is insolvent. Pay-when-certified clauses, which key your release to certification under the main contract, are a different thing and are common. Read the release clause in your subcontract.

Can I charge interest on late retention?

Yes. Once the final date for payment has passed it is a late commercial debt and statutory interest applies at 8% above the Bank of England base rate, unless the contract provides its own substantial remedy for late payment.

Is VAT charged on retention?

Only when the retention is paid or invoiced, whichever is first. Until then there is no tax point for that part of the supply.

What happens to retention if the main contractor goes bust?

Unless the retention was held in a separate trust account, you rank as an unsecured creditor for it. That is the strongest reason to apply for each release on the day it falls due rather than letting it roll into a final account.

This calculator is a free tool for general guidance and is not legal, contractual or financial advice. Release dates are calculated from the practical completion date, the defects period and the payment terms you enter; your contract's actual terms and certificates govern what is due and when. Interest figures use the statutory rate under the Late Payment of Commercial Debts (Interest) Act 1998.